Chiller Part Load Performance — Real Indian Project Case Studies

Chiller Part Load Performance — Real Life Case Studies

Chiller data sheets tell one story. The plant room tells another. After commissioning, measured performance rarely matches rated IPLV — and the gap is usually larger than engineers expect. Here are four Indian project case studies that reveal the real-world factors affecting chiller part load performance.

Case Study 1 — 5-Star Hotel, Mumbai (800 TR Water-Cooled Centrifugal)

Project Overview

Parameter

Design Value

Measured at 12 Months

Chiller capacity

800 TR

780 TR (cooling tower limitation)

Design full load COP

6.1

5.4

Rated IPLV

8.2

6.3 (measured average)

Condenser water supply temp

32°C

35.5°C (monsoon peak)

Chilled water ΔT

5°C

3.8°C (AHU coil fouling)

Annual energy (predicted)

42,00,000 kWh

51,50,000 kWh

Root Causes of Performance Gap

  • Cooling tower approach temperature — design assumed 4°C, actual was 6.5°C due to scale buildup on fill media
  • Chilled water delta-T collapse — AHU coils partially blocked by biofilm, reducing ΔT from 5°C to 3.8°C
  • Condenser pump VFD set to constant speed — missed 12% energy saving opportunity
  • Refrigerant charge slightly low — factory commissioning issue not caught at site

Corrective Actions and Result

  • Cooling tower chemical dosing programme implemented — approach improved to 4.8°C
  • AHU coil cleaning programme quarterly — ΔT recovered to 4.5°C
  • Condenser pump VFD enabled — 11% reduction in pump energy

After corrections, measured average efficiency improved to 7.1 (vs rated 8.2). Remaining gap attributed to actual ambient conditions being higher than AHRI standard test conditions.

Case Study 2 — IT Park, Bangalore (3 x 300 TR Air-Cooled Screw)

Project Overview

Parameter

Design Value

Measured at 6 Months

Chiller capacity

3 x 300 TR

840 TR available (one chiller derated)

Design full load COP

3.2

2.7

Rated IPLV

4.1

3.6

Ambient design temperature

35°C

38°C (one afternoon per week peak)

Actual loading pattern

Mixed — 40–90%

Predominantly 50–70%

Key Finding

One of the three air-cooled chillers was derated because the condenser air inlet was receiving recirculated hot air from the adjacent chiller. The 3-metre gap between units (as designed) proved insufficient in the enclosed roof-level plant area. Effective ambient temperature for the middle unit was 42°C — 7°C above design.

Lesson for MEP Engineers

  • Air-cooled chiller spacing should be minimum 4–5 metres side-to-side in enclosed areas
  • Computational fluid dynamics (CFD) analysis recommended for roof-level chiller plants with multiple units
  • Condenser air discharge direction should be verified against prevailing wind direction
  • Derate air-cooled chillers by 3–5% COP for every 5°C above rated ambient

Case Study 3 — Government Hospital, Delhi (500 TR Water-Cooled Screw, 24×7)

Project Overview

Parameter

Design Value

Measured at 18 Months

Chiller capacity

500 TR

500 TR

Full load COP

5.6

5.1

IPLV

6.8

5.9

Part load operation

Expected 40–80%

Actual 85–100% (undersized)

Redundancy utilisation

100% standby

Standby runs every day

Key Finding

The hospital was designed for 500 TR but actual load reached 550 TR by Year 2 due to additional medical equipment installations not accounted for in the original brief. Both chillers ran at near full load daily, eliminating the part load advantage that drove the IPLV selection.

Lesson for MEP Engineers

  • For hospital projects, add 15–20% future load allowance to the calculated peak load
  • Medical equipment load is frequently underestimated — liaise with medical planner during design
  • IPLV benefits only materialise if the chiller actually operates at part load — check the load profile
  • Consider N+1 redundancy with capacity to absorb 30% future growth

Case Study 4 — Shopping Mall, Hyderabad (2 x 600 TR + VFD, Variable Primary)

Project Overview

Parameter

Design Value

Measured at 24 Months

Chiller configuration

2 x 600 TR VFD centrifugal

As designed

Design IPLV

10.2

9.8

Measured average kW/TR

0.36

0.38

Annual energy (predicted)

65,00,000 kWh

67,20,000 kWh

Prediction accuracy

96.8%

Key Finding

This was one of the best-performing projects in the case study set. Variable primary pumping with VFD centrifugal chillers delivered near-predicted performance. Key success factors:

  • Commissioning was conducted over 3 months including full load and part load testing
  • Condenser variable flow implemented — reduced condenser pump energy by 18%
  • BMS trending enabled monthly performance reporting and early fault detection
  • Chilled water ΔT maintained at 8°C (high ΔT system) — reducing pumping energy significantly

Summary — Key Lessons Across All Cases

Issue

Frequency

Impact on Efficiency

Prevention

Cooling tower scaling / fouling

Very common

5–15% COP reduction

Chemical treatment programme

Chilled water ΔT collapse

Common

10–20% energy increase

Regular AHU coil cleaning

Air-cooled condenser recirculation

Moderate

10–20% derating

CFD analysis, adequate spacing

Incorrect refrigerant charge

Occasional

5–8% COP reduction

Factory test + site commissioning

Load underestimation

Common (hospitals, data centres)

IPLV benefit lost

15–20% design margin

Missing VFD on condenser pump

Common

8–15% missed saving

Specify VFD as standard


Related Reading on MEPVAULT

Continue your research on related topics from our engineering library:

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top